PPG/SEM Products Manufacturing Plant

Location

York, South Carolina

Project Description

Create a catch basin for any spills which may occur during the offloading of a tanker truck.

Scope of Work

  • Structural plans for a 14,000 gallon below grade catch basin. 

  • Civil Site plans for layout, curb locations, protective barriers, erosion control, grading, etc. 

Key Challenges

  • Staging/sequencing plans to maintain an open lane of traffic for tractor trailer deliveries to factory. 

  • Site geometric constraints: keeping any construction activities between curb lines, etc. 

  • Keeping future site improvements in mind with final construction planning. 

Project Team

Project Status

  • Completed